13.10.2002 Embah Engineering Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Comfort Rubber, Taiping.
23.10.2002 Best Wide Corrosion Design engineering data acquisition and soil resistivity test for PBAPPSB Water Main’s Hajjah Rahmah ICCP system.
10.11.2002 Excell Oilfield Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Taima Casting, Senai.
25.11.2002 PB Gas Development of Putrajaya – Precint 11 Phase II Project : Cathodic protection works for construction and commissioning of the relocation of NPS 20” Diameter Serdang Lateral for Petronas Gas Bhd.
9.12.2002 Ho Hup Construction Co. Cathodic protection monitoring for Putrajaya Precint 2 (Core Island) inclusive of mobilisation, demobilisation, equipment, consumables and report writing.
24.12.2002 Gas Malaysia Investigation of low cathodic protection reading & magnesium anode installation at PGW-Area Station 01.
15.01.2003 Raslow Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Puchong Looping.
26.02.2003 Raslow Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Seksyen 16, (Phase II) Shah Alam.
20.03.2003 Right Gas Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Tebrau FL1/DL1, Johor.
25.03.2003 Embah Engineering EPCC of SACP system for gas pipeline relocation works at Jalan Ipoh -Butterworth, Kamunting.
11.04.2003 Embah Engineering Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Hyatt Regency Saujana, Subang.
13.05.2003 MMC Engineering Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Beranang FL1/DL1 Package 1, Nilai & Pajam, NS.
13.05.2003 Embah Engineering Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Kesas Highway Crossing (Reinforcement), Shah Alam.
16.05.2003 Embah Engineering Installation of sacrificial CP system for EPCC of NGDS to Hyatt Regency Saujana, Subang.
22.05.2003 Sedia Engineering Installation of 48 test posts c/w sacrificial anode groundbeds, reference electrode and spark gap in Nilai, NS.
23.05.2003 Pembinaan Sha Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Nibong Tebal FL1/DL1, Penang.
17.06.2003 K & K Sepadu Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Teluk Panglima Garang FLI/DLI, Kuala Langat, Selangor.
24.06.2003 Applied Industrial EPIC of SACP system for gas pipeline to JW Marriot Hotel and Starhill, Kuala Lumpur.
24.06.2003 Applied Industrial EPIC of SACP system for gas pipeline to Duta Plaza, Kuala Lumpur.
1.07.2003 MMC Engineering Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Cheng FL1/DL1 Melaka.
15.07.2003 MMC Engineering EPIC of SACP system for gas pipeline to Kao Soap, Acid Chemical International and Danisco factories in Prai.
20.08.2003 Applied Industrial EPIC of SACP system for gas pipeline to KGNS, Kelana Jaya.
5.09.2003 Applied Industrial SACP system for 20KL LPG underground tank at Ampang Hospital, Kuala Lumpur.
10.09.2003 Right Gas Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Pasir Gudang Package 1.
10.09.2003 Right Gas Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Pasir Gudang Package 2.
10.09.2003 Right Gas Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Pasir Gudang Package 3.
26.09.2003 Embah Engineering Replace cathodic protection test station at TP17, Taiping.
26.09.2003 Embah Engineering Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to MCB, Kamunting.
30.09.2003 Electroscon Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Kluang FL 1/03, Johor.
1.10.2003 Intestmal TERM CONTRACT for cathodic protection and DCVG survey for MTBE Plant and Pipelines MTBE-Port Storage.(Contract duration : 1 October 2003-30 September 2005)
7.10.2003 MMC Engineering Soil resistivity test, foreign structure test facilities and system installation & commissioning at CH 0.00 and CH 1475, Nilai.
7.10.2003 MMC Engineering Supply, install, test and commission SACP system for steel riser at four service stations in Prai 3 & 4.
7.10.2003 MMC Engineering Supply, install and commission SACP system to upgrade protection level at test station (TP#8) and three GMB’s service stations in Prai 1 & 2.
10.10.2003 Embah Engineering Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to the Curve, Damansara.
8.11.2003 MMC Engineering Design, supply, install and commission SACP system for steel riser service station, Ayer Keroh.
1.12.2003 Raslow Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Central Sugar, Shah Alam.
1.12.2003 Raslow Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Seksyen 17, Petaling Jaya.
13.12.2003 Embah Engineering Supply, supervise, install and test cathodic protection system at Mont Kiara Service Station, Kuala Lumpur.
19.12.2003 MMC Engineering Soil resistivity, engineering design, supply, install and commission SACP system for steel riser service station, Prai.
6.01.2004 Right Gas Provision of manpower, equipment, material, consumables to install cathodic protection system for gas pipeline to PREMIUM VEGETABLE OIL, Jalan Timah 2, Pasir Gudang Package 3.
6.01.2004 Right Gas Provision of manpower, equipment, material, consumables to install cathodic protection system for gas pipeline to EONLIPIDS, Jalan Keluli 7, Pasir Gudang Package 1.
6.01.2004 Right Gas Provision of manpower, equipment, material, consumables to install cathodic protection system for gas pipeline to PGEO, Jalan Tembaga 2, Pasir Gudang Package 2.
16.01.2004 K.S. Tan Engineering EPCC of SACP system for NGDS to Pan Pacific Hotel, Glenmarie Shah Alam.
20.01.2004 Embah Engineering To supervise and undertake cadwelding works and concrete works to replace damaged Test Post 2, Taiping.
9.02.2004 Excell Oilfield Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Gebeng FL1/DL1 Stage 1/03, Kuantan.
20.02.2004 Embah Engineering Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Prai FL Stage 1/03, Seberang Prai.
27.02.2004 MMC Engineering Soil resistivity, material supply, install and test monitoring facilities at PGB-GMB pipeline crossing in Pajam, NS.
27.02.2004 MMC Engineering Supply, install and commission SACP system for steel riser @ service stations (SANCHEM, AMSTRONG 1, POLYGLASS, FOUNDRY AND NAFTHA FACTORIES), Prai Industrial Area.
1.03.2004 Raslow Engineering, supply, installation and commissioning of cathodic protection system for EPCC of NGDS to Box Pak Sdn. Bhd. Batu Caves.
11.03.2004 MMC Engineering Installation of SACP system for NGDS to PGEO EDIBLE OIL, Prai.
25.03.2004 Diversified Design, supply and commissioning of cathodic protection system for EPCC of NGDS to Tampoi & Larkin FL1/DL1 (APOLLO FOOD & UNIVERSAL CABLE), Johor.
30.03.2004 MMC Engineering To replace, relocate all underground CP device and test facilities at Jalan Batang Benar and Pajam, NS.
8.04.2004 MMC Engineering EPIC of CP system for NGDS to KL Bangi Looping, Serdang.
9.04.2004 Konsortium Yeong Repair of GMSB CP Test Post along Jln Haji Sirat, Meru, Klang.
21.04.2004 Right Gas Supply and installation of SACP system at Balakong inclusive of Close Interval Potential (CIP) Survey.
21.04.2004 Right Gas Provision of manpower, equipment, material, consumables to install cathodic protection system for NGDS to Kulai FL Stage 1/04, Johor.
21.04.2004 Right Gas Provision of manpower, equipment, material, consumables to install cathodic protection system for NGDS to GUAN CHONG COCOA, Pasir Gudang.
26.04.2004 MMC Engineering Design, supply, supervision and commission of CP system for NGDS to Dengkil FL Stage 1/03.
20.05.2004 Eurowide Construction of roadworks, roadside drains, sewer reticulation and sewage pump station (RP2) for package 2 at proposed integrated township development of Bandar Bukit Raja (Stage 1) on lots 19, 25, 27, 52, 1635, 13046 & 13047, Mukim Kapar, Daerah Klang. -Relocation and re-position of test post for Bukit Raja Main Infra Project at Jalan Haji Sirat, Klang.
25.05.2004 MMC Engineering EPIC of CP system for pipeline underneath tarred road, Dengkil.
26.05.2004 Embah Engineering Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Kelana Jaya DL Stage 1/03, Selangor.
10.06.2004 Changkat Ressam EPIC of SACP for 3600m of NPS 6”, Nilai Industrial Area.
21.06.2004 SAAG - Embah Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Pasir Gudang Stage 2/03, Johor.
21.06.2004 MMC Engineering Engineering, supply, supervision and commissioning of cathodic protection system for NGDS to PETRONAS NGV Station, UPM.
30.06.2004 MMC Engineering Relocate Petronas Gas test station, Beranang.
30.07.2004 Pembinaan Sha Cathodic protection subcontract for NGDS to Malayawata, Prai.
14.08.2004 Right Gas Cathodic protection upgrading works and Close Interval Potential (CIP) Survey.
9.09.2004 Electroscon EPIC of SACP system for NGDS to Batu Caves FL Stage 1/04, Selangor.
29.09.2004 Masmirin Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Nibong Tebal (Additional Works).
18.10.2004 Changkat Ressam EPIC of SACP system for gas pipeline to Nilai Industrial Area.
18.10.2004 Rightgas Replace magnesium anode at GROBEST Service Station.
18.10.2004 Rightgas Relocate PETRONAS GAS test post station at PGU Right of Way and provision of resistive bond box at GMB-PGB inter-pipeline crossing, Tebrau.
18.10.2004 Rightgas Replace magnesium anode at IFFCO Service Station.
18.10.2004 Rightgas Supply, installation and commission additional CP system for NPS6” from CH275B to CH390B at Jalan Tembaga 2, Pasir Gudang.
18.10.2004 Rightgas Investigate and rectify damaged cables at Test Station TS#5 along Jalan Besi 1, Pasir Gudang.
18.10.2004 Rightgas EPIC of CP System to Pasir Gudang & Johore Port FLDL Stage 1/04, Johor.
18.10.2004 Rightgas NGDS to Senai DL Stage 1/04, Johor
18.10.2004 Diversified Engineering Engineering, supply, supervision and commissioning of cathodic protection system for NGDS to Kamunting FL DL Stage 1/03, Perak.
26.11.2004 Diversified Engineering Engineering, supply and commissioning of cathodic protection system for NGDS to Convention Centre, Precint 5, Putrajaya.
26.11.2004 Diversified Engineering Engineering, supply and commissioning of cathodic protection system for NGDS to Johor Port FL/DL Stage 1/03, Johor.
12.12.2004 Diversified Engineering Engineering, supply and commissioning of EPCC of NGDS to Bukit Kemuning FL Stage 1/04, Selangor.
22.12.2004 Applied Industrial Supply, install, testing and commissioning of cathodic protection system for NGDS to Shah Alam FL DL Stage 1/04 Seksyen 26.
22.12.2004 Diversified Engineering Engineering, supply, supervision and commissioning of cathodic protection system for NGDS to Takeuchi, Tebrau.
22.12.2004 Masmirin Engineering, supply, supervision and commissioning EPCC of NGDS to Kuantan Port FL Stage 1/04, Pahang.
7.01.2005 Right Gas EPIC of cathodic protection system for NGDS to Skudai & Tampoi FL Stage 1/04, Johor.
10.01.2005 DEC Design, supply and commission CP system for PNGV Telok Panglima Garang .
12.01.2005 Peremba Construction Subcontract for the cathodic protection design engineering and system commissioning for Melut Basin Oil Development Project, Sudan.
15.02.2005 Petronas Penapisan (T) TERM CONTRACT for inspection and maintenance of cathodic protection system at Kerteh Refineries (KR1 and KR2 Plants), 3+1 Year Contract.
17.02.2005 Inter Region Soil resistivity test and CP design for gas pipeline relocation works at Taman Putra, Kluang.
18.02.2005 Diversified Engineering Engineering, supply, supervision and commissioning of cathodic protection system for NGDS to Apollo Food and Universal Cable
18.02.2005 Diversified Engineering Engineering, supply, supervision and commissioning of cathodic protection system for NGDS to Kemuning FL stage 1/04, Bukit Kemuning, Klang, Selangor.
25.02.2005 Applied Industrial EPIC of SACP for NGDS to Alor Gajah FL DL Stage 1/04.
1.03.2005 Petronas Gas Cathodic protection services for PGU2 Sector 1, Loop 1, PGU 2 Sector 2, Loop 2, CP1 Jeram to CP2 Tg. Karang for MIS technical department ,PGB-TOD Segamat.
17.03.2005 Total Sterling Provision of upgraded CP design inclusive of site assessment, pipe to soil potential, soil resistivity test, for PD Lateral/Loop Pipelines for PGB Seremban.
17.03.2005 Intestmal EPCC of new impressed current cathodic protection anode ground bed at CP2 Kuala Kuantan for PGB Kuantan RO.
21.03.2005 PFC Engineering EPCC of cathodic protection system for PASB OSBL Piping Project, Kerteh.
22.03.2005 Inter Region Undertook current drainage test at HDD Pipeline Section at Taman Putra, Kluang.
23.03.2005 MMC Engineering Installation of CP system for EPCC of NGDS to Cheng FL1/DL1 Melaka. (Additional works).
29.03.2005 MTBE Malaysia Repair of pipeline cathodic protection cable for test point TSS 8A (Pipeline MTBE – Port Storage).
30.03.2005 MMC Engineering EPCC of NGDS to Beranang Package 1, Nilai & Pajam, Negeri Sembilan.
28.04.2005 Bumi Focus EPIC of cathodic protection system for EPCC of NGDS to Senai FL Stage 1/05, Johor.
3.05.2005 Peremba Provision of manpower , tools, equipment and material to carry out the cathodic protection system installation and supervision for tank base for Marine Terminal Facilities in Sudan.
22.05.2005 Bumi Focus Relocation of CP test post along Jalan Haji Sirat, Meru, Klang.
27.05.2005 PBJV Engineering, supply and commissioning of SACP system for NGDS to Ayer Keroh FL DL Stage 1/05, Melaka.
27.05.2005 PBJV Engineering, supply and commissioning of SACP system for NGDS to Batu Berendam FL DL Stage 1/05, Melaka.
8.06.2005 Masmirin Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Prai FL Stage 1/05, Prai.
9.06.2005 Bumi Focus EPIC of cathodic protection system for EPCC of NGDS to Senai FL Stage 1/05, Johor.
9.06.2005 Inter Region Supply, install, and commission SACP for gas pipeline relocation works at Taman Putra, Kluang.
13.06.2005 Masmirin Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Sitiawan, FL Stage 1/05, Sitiawan.
16.06.2005 Petronas Gas Cathodic protection services for NPS 36 PGU Loop 1 pipeline from Kerteh Compressor Station, Kerteh-ML200 Segamat and NPS 6 Propane and Butane Pipeline from M1 Teluk Kalong to MTBE Station in Gebeng.
4.07.2005 Misi Setia Oil & Gas Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Sitiawan FL Stage 2/05.
4.07.2005 True Features Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to PJ FL Stage 1/05, Petaling Jaya.
4.07.2005 Bumifocus EPIC of cathodic protection system for EPCC of NGDS to Segambut FL Stage 1/05, Kuala Lumpur.
8.07.2005 Right Gas Cathodic protection system for HDD pipeline section, Skudai.
8.08.2005 Haven Corrosion Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of CP System for Town Water and Fire Water at Tanjung Bin Power Plant.
12.08.2005 Bumifocus EPIC of cathodic protection system for EPCC of NGDS to Kossan Rubber, Meru, Klang.
29.08.2005 Masmirin Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Nibong Tebal FL Stage 1/05.
14.09.2005 Petronas Gas Contract for PCC of new impressed current cathodic protection system at CP10 Kg. Sega, Seremban.
19.09.2005 Masmirin Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Prai FL Stage 3/04, Seberang Prai.
7.11.2005 Pembinaan Naga Cathodic protection for internal pipeline at Southern Steel, Prai Industrial Area, Penang.
25.11.2005 Bumifocus EPIC of cathodic protection system for EPCC of NGDS to Tebrau DL Stage 1/05, Johor.
13.12.2005 Petronas Gas Supply, delivery, replace, install, test and commission new CP test posts for PGB-TOD Shah Alam.
28.01.2006 Rantau Padu Commissioning of CP system for Effluent Water Surge Tank A & B at TCOT, Kerteh for Exxon Mobil.
5.02.2006 Local Engineering Complete CP system audit survey (CIPS, DCVG, interference test, potential measurement) and repair works at Onshore Gas Terminal, Kerteh for Petronas Carigali Sdn Bhd.
8.02.2006 Masmirin Design, supply, supervision and commissioning of cathodic protection system for EPCC of the NGDS to Prai FL DL Stage1/05.
15.02.2006 Safemac EPIC of impressed current cathodic protection system for fire water and oily sewer water piping at PP(M)SB Co-Generation Plant, Melaka for PP(M)SB, Melaka.
3.03.2006 Changkat Ressam Improvement of pipe-to soil-potential at GOODWAY, in Nilai.
8.03.2006 Bumifocus Supply manpower and material/consumables to upgrade CP system in Senai.
21.04.2006 MMC Engineering Design and commissioning of CP system for pipeline installation to CAMPBELL.
2.05.2006 PBJV Group Supply, install, test additional CP system at Ayer Keroh FL Stage 1/05 complete with CIP survey.
19.05.2006 Petronas Gas Contract for EPIC of replacement of existing impressed current cathodic protection anode groundbed with new anode groundbed for CP#2 Tenang, Labis, Johor.
31.05.2006 Misi Setia Oil & Gas Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Prai FL Stage 1/05 & FL DL Stage 1/05 (LOOPING 1 & LOOPING 2), Prai.
15.06.2006 MMC Engineering Cathodic protection rectification works for EPCC of NGDS to Ayer Keroh FL1/DL1.
15.06.2006 Masmirin Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Kulim Hi-Tech FL Stage 1/06, Kulim.
15.06.2006 MMC Engineering Cathodic protection rectification works for NGDS to Beranang FL DL Stage 1/05.
15.06.2006 MMC Engineering Cathodic protection rectification works for NGDS to Cheng FL1/DL1, Melaka.
9.08.2006 Petronas Gas SERVICE AGREEMENT corrosion control for underground pipeline for a period of two (2) years with an extension for another one (1) year for PGB-Transmission Operation Division, Segamat.
15.08.2006 Petronas Gas CP Enhancement of NPS 18” PD Lateral Pipeline at TTJ Power Station, Port Dickson.
18.09.2006 Misi Setia Oil & Gas Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Klang FL Stage 1/06 (Reinforcement) Jalan Johan Setia, Klang.
3.10.2006 Petronas Gas Magnesium ribbon installation for NPS36 PGU 2 Sector 1 & LOOP 1 pipelines at Sg. Ular & Kuala Kuantan.
30.01.2007 Total Sterling Inspection of GPP B cathodic protection system (tank and fire water pipeline) and rectification works.
14.02.2007 Hablem Oil & Gas Inspection and maintenance works of CP system at PROTON, Shah Alam.
28.02.2007 Total Sterling EPIC of ICCP anode groundbed installation at CP Station Export Terminal, Telok Kalong for Petronas Gas - Kertih RO.
5.03.2007 Petronas Gas EPIC of test post installation at PGU1, PGU2 and Loop 1 mainlines, for Kertih RO.
7.03.2007 Alam Gas Inspection of cathodic protection system at First World Hotel, Genting Highland.
27.06.2007 Ikon Subsea Provision of cathodic protection system services for PCC 2 Labuan Gas Terminal (LGAST) & pipeline project, Labuan for Petronas Carigali Sdn. Bhd.
5.07.2007 Petronas Gas Resistive bonding for NPS8 Shah Alam NGV Lateral.
22.07.2007 Total Sterling Supply, replace and commission the underwater sacrificial anode for CP system at Export Terminal Jetty, Telok Kalong.
30.07.2007 MTBE Malaysia Contract for EPIC of MTBE, PDH and PPM plant cathodic protection revamp work.
10.08.2007 Petronas Gas/td> Magnesium ribbon installation for NPS36-inch PGU 1.
10.08.2007 Petronas Gas Magnesium ribbon installation for NPS36-inch PGU 1.
10.08.2007 Petronas Gas Magnesium ribbon installation for NPS8-inch C3/C4 KCS to ET.
20.08.2007 Inter Region Replacement and relocation work of cathodic protection post at Tronoh, Perak.
20.08.2007 Misi Setia Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Ijok- Sg. Buloh Looping Stage 1, Selangor.
30.01.2008 Petronas Gas Magnesium ribbon installation for NPS8 C3/C4 KCS to ET.
31.01.2008 Sidenco EPIC of cathodic protection system for engineering, procurement, construction & commissioning of Ethane Supply Reliability Improvement to OPTIMAL Project.
31.01.2008 Petronas Gas Magnesium ribbon installation for NPS 36 PGU 1.
23.02.2008 Safemac EPIC of ICCP system for underground pipeline for Cogen Expansion project for PP(M)SB, Melaka.
9.04.2008 PFCE-CG YEARLY TERM CONTRACT (3+1) for cathodic protection services at OPTIMAL (M) Sdn Bhd, Kerteh, Kemaman.
20.05.2008 Petronas Gas EPCC of SACP system for underground pipelines at Gas Processing Plant, Complex B.
29.05.2008 Inter Region Replacement & relocation work of cathodic protection test post at Tronoh, Perak.
27.06.2008 Misi Setia Design, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Telok Kalong FL Stage 1/08, Telok Kalong, Kemaman, Terengganu.
4.08.2008 Petronas Gas CP Verification on Prai & Gelugor and Prai Lateral.
8.10.2008 Masmirin Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Kulai FL Stage 2/08, Kulai, Johor.
16.02.2009 Optimal Olefin Contract for provision of engineering, procurement, construction & commissioning services for capacity increase of cathodic protection system project.
22.03.2009 PFCE-CG Cathodic protection cross bonding installation at MeOH and H2SO4 pipelines.
07.05.2009 Masmirin Mobilisation & demobilisation of CP engineer to conduct pre-comm and commissioning of CP system for Stage 2 &3 pipelines. Kulai, Johor.
19.05.2009 Petronas Gas PRICE AGREEMENT for corrosion services for PGB TOD pipeline systems for a period of two (2) years with an option to extend of one (1) Year. (Contract Period : 1.6.2009 – 31.5.2011).
23.07.2009 Fusionspace Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Taman Makmur FL Stage 1/08,Kulim, Kedah.
5.11.2009 Petronas Gas Sacrificial ribbon anode installation and CIP survey for NPS16” Telok Kalong Lateral and NPS4” Export Terminal Lateral.
26.11.2009 Fusionspace Engineering, supply, supervision and commissioning of cathodic protection system for EPCC of NGDS to Sungai Petani FL Stage 1/09,Sg Petani.
24.02.2010 Petronas Gas Test post installation for NPS30 PGU2 Sector 3.
2.03.2010 Petronas Gas Sacrificial ribbon anode installation and CIP survey for NPS16” Telok Kalong Lateral, NPS6” C3 Lateral and NPS4” Export Terminal Lateral.
17.03.2010 Petronas Gas Test post installation for C3/C4 and Export Terminal Lateral.
23.04.2010 Applied Industrial EPIC of cathodic protection system for gas pipeline at Precint 11 –Stage 2, Putrajaya.
25.05.2010 Applied Industrial EPIC of cathodic protection system for Buried 20KL LPG Storage Tank at Intermark Mall, Kuala Lumpur.
1.06.2010 Petronas Gas Repair CP1 Sungai Ular, Cherating.
13.07.2010 PP(T)SB Contract for design, supply, installation, testing and commissioning of impressed current cathodic protection system for D919 & D920 aboveground storage tanks.
4.03.2011 Petronas Gas CP test post repair & maintenance for Pasir Gudang Regional Office.
15.5.2011 Optimal Chemical TERM CONTRACT for provision of cathodic protection plant preventive maintenance for a duration of 2 years (15.5.2011 – 14.5.2013).
16.5.2011 Petronas Gas PRICE AGREEMENT for corrosion services & line pipe preservation program for PGB TOD pipeline systems for a period of two (2) years with an option to extend of one (1) Year. (Contract Period : 1.6.2011 – 31.5.2013).
22.07.2011 Applied Industrial EPIC of cathodic protection system for gas pipeline at Precint 8, Putrajaya.
16.08.2011 Petronas Gas Excavation & test post installation for ML112-ML200
16.08.2011 Gas Malaysia To supply, install, test and commission 24 missing SACP systems at Bestari Jaya, Bukit Badong and Ijok, Kuala Selangor.
29.09.2011 PP(M)SB Contract for refurbish cathodic protection system at Marine Jetty CB1 – LPG for PP(M)SB.
29.09.2011 Petronas Penapisan Contract for provision of cathodic protection system deepwell groundbed repair works at Process/Utility Units for PP(M)SB
20.10.2011 Petronas Gas MINOR ONSHORE FABRICATION – CIVIL ENGINEERING - To replace & install new CP test post for Shah Alam Regional Office.
2.11.2011 Petronas Gas SACP system for PGU2 Sector 2 Mainline.
30.11.2011 Aqeel Engineering Contract for cathodic protection services at Petronas Gas Bhd, Bandar Indera Mahkota, Kuantan.
28.12.2011 Petronas Gas Installation of test post for SACP system, NPS36” ML207 – Port Klang Metering Station.
14.02.2012 Petronas Gas Onshore pipeline inspection & repair – Test post installation at MLL112 – ML200.
16.03.2012 Pahlawan Power Maintenance of cathodic protection system at Tanjung Kling Power Station, Melaka.
29.03.2012 Seri Ibai Enterprise Cadangan membina dan menyiapkan jalan masuk utama ke Bandar Kijal, Kemaman - cathodic protection mitigation system for PGU pipeline system under road crossing.
23.05.2012 Petronas Gas Contract for design, excavation, material supply & installation of pre-packaged magnesium anodes at Gas Processing Plant, Complex B.
29.05.2012 Optimal Chemicals Contract to perform troubleshooting for CP system at EOG Cooling Water Piping (CW & CWR pipeline) & Tank D-6907 due to insufficient protection.
14.08.2012 Petronas Gas EPIC of new impressed current anode groundbed at Airstrip CP Station, Miri.
29.08.2012 Petronas Gas Contract for EPIC of SACP system at Gas Processing Plant Complex A, Kerteh.
18.09.2012 PAC Builders Provision of manpower, equipment, material, consumables and tools to undertake reference electrode & test post installation at AMC – PGB Road Crossing at Lot 24 AMC, Gebeng.
1.11.2012 Petronas Gas PRICE AGREEMENT for engineering, procurement, installation and commissioning of new distributed anode ICCP systems for underground piping at station’s TOD, PGB for a period of two (2) years with an option to extend another one (1) year.
8.11.2012 Petronas Gas Excavation and test post installation at KP107, PGU2 Sector 1 Pipeline, Segamat RO.
9.04.2013 ML Sepakat Sdn Bhd Design, engineering, supply material & installation of cathodic mitigation equipment in Kempas, Johor.
7.07.2013 Petronas Derivaties TERM CONTRACT for provision of cathodic protection plan preventive maintenance (PPM) at PCDSB for 2 years.(10.7.2013 – 9.07.2015)
25.07.2013 Lembaga Air Perak Design, supply, install & commissioning for cathodic protection mitigation work for PGB gas pipeline crossing with 400mm diamater M.S pipe at Sg Limau, Trong, Taiping, Perak.
16.12.2013 PBJV Group EPIC of CP system & AC Mitigation for EPCC of Prai II Lateral Gas Pipeline Project for PGB.
2.01.2014 Petronas Gas Supply, installation & commissioning CP test post and reference electrodes at Lot Q Crossing, Kertih.
19.03.2014 Applied Industrial Design, supply, installation & commissioning of cathodic protection system at Palm Mall, Seremban.
2.07.2014 Applied Industrial Design, supply, installation & commissioning of cathodic protection system at UIAM Campus, Kuantan.
7.07.2014 PBJV Group Provision of ICCP & magnesium anode system for Dalak pipeline project in Sabah & Labuan for Petronas Carigali Sdn. Bhd.